I think I may now be on to my 4th camera since this job started. Building sites are a tough environment for a camera, but I'm getting fed-up with the lenses packing up in just a matter of months. Now I have one which is claimed to be shock proof and waterproof, and has not protruding lens. Unfortunately, as a downside, the photos are rubbish. Anyway, that's the reason for the delay, and for the missing bits from this post.
Here is a shot of the north gable with the final 2 windows in place:
To complete the insulated envelope of the house I moved to the southern end of the building, to work on the little triangle on the eastern elevation above the new lounge roof. The render here was the only bit of original render left on the house, saved by being in the roof-space of one of the lean-tos that I demolished a couple of years ago. This is a close-up showing the pargetting pattern, made just by dipping the point of a trowel into the setting render:
I cut a large piece to put aside for posterity, then pulled the rest off, revealing a large rat's nest:
I did the usual clean up of the frame, then Celotex between the timbers:
This next photo shows the wall finished, but is out of order because it also shows the little roof finished too, and there was lots of work in that:
Here are the tiles. What you can't see is that probably a quarter of the tiles are cut. This is the most complicated bit of roofing I've done:
The lead flashing over the top of that pitched roof was a bit awkward, but worked out well. Here are a couple of the clips I used:
This shows half of the cover flashing in place, with the welt prepared and the clips folded up to retain the flashing in place:
The reason it is made in two halves is twofold. Firstly, it is over 1.5metres (5 feet in old money) long, and single piece of lead on a roof should be over this length. Secondly, there is an awkward end to each piece (at the left hand end of the above photo), and it would be very difficult to get a whole piece into position with that going on at each end. Below is the finished flashing, with some little cover pieces at each end tucked under the next row of tiles, and having been cleaned up with patination oil ( a must for new leadwork, as it prevents staining of the roof below):
After doing the other end the following day, I went back and siliconed up any suspect areas with a low modulous silicon. Anyway, here is the other end:
This is the temporary platform I made to access the area:
Another reason for not posting is that pictures of feather-edge boards being painted is not the most riveting thing on the planet. So here you are:
That's a mist coat and a full coat on both sides of 24 boards, plus some 2x1s and some 4x1s. I shall be cladding the two single storey parts of the house in the next few days. It's 2 coats of paint pre-fitting, and another post fitting, and i always, always paint both sides. I also check that any contractors working on jobs I've specified have done both sides of the boards..........for stability, avoidance of cupping, but also because moisture can easily run down the back of the boards.
We've got a front door! OK, it's a temporary one, being an old internal door, but it does mean that we can finally go out and leave the house locked up for the first time since about April. The bottom of the door is approximately finished floor level, so the scrap of ply screwed to the bottom shows the thickness of the build-up of insulation and screed to come:
Now, on to the utility room roof. Firstly, I set out the tiles to determine the verge overhang:
Then I cut back the battens and roofing membrane to suit, before inserting the slate undercloak, which is trapped in place by the battens squeezing it down onto the end rafter. I had deliberately left the last nail in the battens out, and the next-to-last nail "up" (ie not driven home) when I did the felt-and-battens a year or two ago, to facilitate the fitting of the undercloak. Anyway, here are the verges ready for tiles:
My general plan is to board the little areas between the two main bodies of the house, then tile the utility roof and do the feather-edge cladding to the utility and the lounge single storey outshots. Then I'll either slate the lounge roof, or do the brickwork plinth (and the fake chimney). It is too late in the year to be doing lime rendering, so that will have to wait for spring. After the plinth and lounge roof (and my workshop roof), I'll focus on internal walls and floors, to be ready to entertain 11 for christmas dinner.